Sunset Acres Subdivision Improvements

Phase 1 

This project consists of the following improvements:

  • Detention pond: Design and construction of detention pond is required to limit the additional storm drain capacity that can be accommodated within TxDOT right-of-way.
  • scope includes filed survey, subsurface utility engineering, geotechnical survey, detailed design and bidding and construction services

Total estimated construction cost is approximately $1.5 Million.

 

Phase 1 Schedule

Design Phase Completion – May 2021

Bidding Phase Completion – January 2022

Construction Phase Completion – August 2022

 