Project Name: Feltner Alley Wastewater Replacement
Current Update: 03/2022
Work Completed Last Month: In February, crews Installed the wastewater main and manhole
Work Planned This Month: In March crews will install asphalt on trench repair and begin site clean up
Construction Completion: March 2022