Project Update - November 2019

  • Camacho paved with asphalt from Patton to Hull Street

  • Road base being installed on MacArthur between Hull and Armstrong

  • Concrete curb and gutter, driveways and sidewalk being installed on MacArthur between Hull and Roosevelt

  • Water and wastewater lines on Armstrong complete

  • Excavation on Armstrong to follow between Churchill and MacArthur

We're here if you need us: 

After hours - David VanDyke, Cox Construction - 512.618.2249

Damage claims - Cindy Conyers, City of San Marcos - 512.393.8065

Towing issues/expenses - Rey Garcia, City of San Marcos - 512.393.8143

General questions, concerns - Nancy Hyde, City of San Marcos - 512.393.8130