Schedule and Budget

  • Construction Start: Summer 2017
  • Pipeline: Construction complete by January 2019 
  • Elevated Storage Tank: Construction complete by September 2019
  • Pump Station Upgrades: Construction start March 2019 complete by September 2019
  • Construction Cost: $7,700,000

Rey Garcia, P.E. is the project manager. Contact Rey here