Project Update - July 2020

**All dates are based off an estimated monthly schedule and are weather dependent**

Wastewater

  • Wastewater main installation continues on Rodriguez 

Water

  • Water main installation continues along Armstrong, Patton and Wavell

Street Work

  • Roadway excavation, flex base installation and preparations for concrete work continue on Alabama, Arizona and Georgia Streets