Phase 1
This project consists of the following improvements:
- Detention pond: Design and construction of detention pond is required to limit the additional storm drain capacity that can be accommodated within TxDOT right-of-way.
- scope includes filed survey, subsurface utility engineering, geotechnical survey, detailed design and bidding and construction services
Total estimated construction cost is approximately $1.5 Million.
Phase 1 Schedule
Design Phase Completion – May 2021
Bidding Phase Completion – January 2022
Construction Phase Completion – August 2022
Phase 2
This project consists of the following improvements:
- North drainage system: includes storm drain design along Parker Drive, Patricia Drive, Ebony Street, Magnolia Drive Lockwood Street, Oakdale Road, and Candlelight Lane.
- South drainage system: includes storm drain design along Broadway Street, Parker Drive, Parkdale Street, Lockwood Street, Candlelight Lane, Patricia Drive, Del Sol Drive and Peter Garza Drive
- Water main replacement along Patricia Drive
- Wastewater line replacement along Parkdale Drive and Broadway Avenue
- traffic calming measures along Broadway Street
- scope includes filed survey, subsurface utility engineering, geotechnical survey, detailed design and bidding and construction services
Total estimated construction cost is approximately $12.0 Million.
Phase 2 Schedule
Design Phase Completion – December 2022
Bidding Phase Completion – May 2023
Construction Phase Completion – January 2025