Red Sky Water Main

Red Sky Water Imp Aerial Overall(20180416)

This project will replace 5,070 LF (approx.) of 2” water line along Horace Howard Dr. with an 8” water line.  This is an area within the City's water CCN (area of Certificate of Convenience and Necessity) where the number of connections exceeds TCEQ requirements. This will also provide fire protection for the area.

  • Construction Cost - $1.0M
  • City PM – Angel Sosa               
  • Design Firm – Walker Partners
  • Construction Start -  January 2020