University Wastewater Line Replacement - October 2020

University-LocationMap2
  • Approximately 95% of the wastewater main has been installed 
  • Paving repairs and striping is expected to occur in mid-October 
  • Road anticipated to be fully open to the public by the end of October
  • Construction is occurring along University Drive from Moon Street to N. LBJ and along N. LBJ from University to Concho Street
  • Traffic is detoured to Hutchison for the duration of the project with University buses allowed to use N. Edward Gary for Texas State campus access