This project will replace an ageing and deteriorated clay sewer line (760 ft.) along Feltner Alley from San Antonio Street to MLK Drive.
Project Status and Schedule
- Plans complete to 60 percent stage
- Construction is anticipated for Autumn 2021
- Project Manager: Kirk Abbott