E Hopkins St - Pedestrian and Bike Improvements - March 2021

Current Update: 03/2021

Work Completed Last Month: Finished installing pedestrian lighting foundations throughout the project and various sidewalk connections.  Due to a delay in signal poles, the contractor will not be able to install mid-block cross-walk at Riverside & the Library until this May/June. Pedestrian Traffic will be re-routed to Aquarena Springs and CM Allen as the sidewalk is replaced between Riverside and Charles Austin.   

Work Planned This Month: Installing sidewalk between Riverside and Charles Austin

Construction Completion: See Dashboard For Details

Pictures from last month: 
Charles Austin Ribbon Curb  (1)Forming SidewalkPouring Sidewalk