Project Update

Project Name: Mobility IH35 - IH35 and Hwy 123 Improvements

Current Update: 1/2022

Work Completed Last Month: Water and wastewater line relocation along SB & NB Frontage Roads north of SH123 is complete

Work Planned This Month: Water and wastewater line relocation along SB & NB Frontage Roads south of SH123

Construction Completion: See Dashboard for Details or visit  https://www.my35.org/capital-project-sh123.htm